Tasks Accomplished
  • 10/18/14 Team completed the Environment Wash Website Test Plan

Tasks in Progress
  • Implementation of website

Tasks Planned For the Next Two Weeks
  • Web Site HE (10/25)
  • Implementation
  • Write the next blog post. (Ben)

Issues
    There are no issues at this time.

Metrics

Time spent:
Stefano: 60 minutes
Ben: 75 minutes
Matt: 70 minutes
Brian: 60 minutes
Team Total: 265 minutes

Running Total:
Ben: 235 minutes  
Brian: 220 minutes  
Matt: 220 minutes  
Stefano: 215 minutes  
Team Total: 890 minutes  