Saturday, September 6, 2014

Status Report for Weeks 1 & 2

    This being this first blog post for the project, it makes sense to do some introductions. The members of Team 3 are Stefano Sansone, Matt Smicinski, Brian Besmanoff and Ben Kantor. The project we have decided to work on this semester is a web application targeted towards concerned citizens who want to contribute to solving environmental problems. Our application will allow users to post and plan environmental cleanup projects in their local communities. Once a project is posted, other users of the site can volunteer to work on said project.
  
    Other than selecting a project, we mainly worked on the initial organizational effort associated with any new project such as establishing weekly meeting times and sharing contact information.


Tasks Accomplished
  • 08/27/14 - The group collaboratively brainstormed three project proposals (30 minutes).
  • 08/29/14 - The group selects the project they will be working on this semester from the three proposals (10 minutes).
  • 09/03/14 - Matt Smicinski setup this blog using Blogger (15 minutes).
  • 09/06/14 - Ben Kantor writes this blog post (20 minutes).


Tasks in Progress
  • Each member of the group is tasked with finding one user for the Requirements Discovery section of the project. (Everyone, 15 minutes).


Tasks Planned For the Next Two Weeks
  • The entire team will need to collaboratively work on and complete the Software Requirements Specification document. (Everyone, Estimate: 2 hours)
  • Write the next blog post. (Brian, Estimate: 20-30 minutes)


Issues


    There are no issues at this time.


Metrics


Time spent:
Stefano: 40 minutes
Ben: 60 minutes
Matt: 55 minutes
Brian: 40 minutes
Team Total: 195 minutes

No running total this week as it is the first week.